Executed Projects
- Moleeta Field Production Facilities
Client: Petrodar Operating Co. Contract Value: 94,231,610.72 US $ Location: Moleeta Duration (month): 24 Months Description: EPCC of Field Production Facilities comprise of 4 Nos. Crude Fluid Processing Trains. - Diffra FPF & Flowlines Project ( Higleig Petrofac J.V)
Client: Greater Nile Petroleum Operating CO Contract Value: 35 million US $ Location: Muglad Basin Duration (month): 11 Months Description: Engineering , Procurement and construction activities for Construction of Field Production Fa cility (FPF) at Diffra and 5 Nos well head areas. - EPCC of Thar Jath Export Pipe line HPSIC/CPEE Consortium
Client: White Nile Petroleum Operating CO Contract Value: 27 million US $ Location: Thar Jath Duration (month): 23 Months Description: EPCC of Thar Jath Export Pipeline mechanical , welding of 86 KM & of 24 Pipeline - Munga Field Development & Pipe Line ( Higleig Petrofac Consortium)
Client: Greater Nile Petroleum Operating CO Contract Value: 25 million US $ Location: Unity State Duration (month): 11 Months Description: Construction field surface facilities that include civil works , services building , R.c.c concrete plus Electrical and Mechanical & Piping work - Moga FPF & Transit Line Poroject
Client: China National Petroleum Corporation International Sudan Contract Value: 21.5 million US $ Location: Moga Duration (month): 22 Months Description: Engineering , Procurement , Construction and commissioning of Moga FPF & Transit Line Project HPSIC executedall the work rquired such as civil earthwork, serviced building, R.c.c concrete plus Electrical and Mechanical piping work and 18km piplin - Palouge Airport
Client: Petrodar Operating Co. Contract Value: 20 million US $ Location: Palouge Duration (month): 23 Months Description: EPCC for Airport at Palouge HPSIC carried out all the works which consist of civil , electrical , telecommunication & mechanical works , 2.5 runway , taxway , terminal building and fuel filing station - Adar /Agordeed FPF Project HPSIC/DODSAL Consortium
Client: Petrodar Operating Co. Contract Value: 18.7 millino US $ Location: Adar Duration (month): 21 Months Description: EPCC for Adar /Agrodeed FPF Project Engineering , Procurement , Consrturction and Commissioning of Adar FPF, HPSIC exucted all the work required such as civil , earthworks services , building , electrical tank erection , mechanical and pipe work. - EPC for Marine Terminal 400,000 BBl storage Tanks (TK107 & K108)
Client: Greater Nile Petroleum Operating CO Contract Value: 16.3 million US $ Location: Bashair Duration (month): 11 Months Description: Engineering , Procurement , Construction and Commissioning for Marine Terminal 400,000 Storage Tanks (TK-107 & TK -108 ) and Associated upgrading at Marine Terminal Facilities. - PCC of WNPOC Accommodation Complex
Client: White Nile Petroleum Operating CO Contract Value: 15.8 millino US $ Location: Thar Jath Duration (month): 22 Months Description: Procurement , Construction & Commissioning of WNPOC base Camp at Thar Jath Area , the Project includes prefabricated building , earth works , electrical , telecommunication & mechanical works. - Field Surface Facilities 1 (Main Contract )
Client: Greater Nile Petroleum Operating CO Contract Value: 13 million US $ Location: Unity oil Field - Unity State Duration (month): 6 Months Description: The works were done in collaboration with sumatec & Name Fatt as Consortium. HPSIC carried out the civil & electrical works , e.g clearance of tight way (50km) , excavation , backfilling . R.C Foundation for pipe supports , transormer & drain pits (500m3) . The Electrical works included erection of 700 electrical poles , installation & stringing of wire of overheadline (80km) , internal connections for 32 wells.i.e.....testing & flow lines. - Civil work in Balila CPF
Client: China Petoleum Engineering Construction Operation Company Contract Value: 10 millino US $ Location: Muglad Basin Area Duration (month): 14 Months Description: HPSIC carried out the civil works which included , earth pad , access roads , bases for oil storage tanks , drainage facilities instation yards , utility bond e.g firewater bond & evaporationbond. The works also included steel pilling for power , other oil structures & residential facilities. - Neem Base Camp
Client: Greater Nile Petroleum Operating CO Contract Value: 9.9 million US $ Location: Neem Duration (month): 20 Months Description: Procurement , Construction and commissioning of Neem Base Camp project includes prefabri cated building , earth works , electrical , telecommunication & mechanical works. - Moleeta Operation Base Camp site Preparation Works
Client: Petrodar Operating Co. Contract Value: 8,828,579.00 US $ Location: Moleeta Duration (month): 9 Months Description: Construction of The operation base camp consist of the following: The size of the camp is 30,000.00 m2 - Bioremediation Expansion Civil Works
Client: Greater Nile Petroleum Operating Company Contract Value: 6,750,000.00 US $ Location: Higleig Duration (month): 8 Months Description: Bioremediation Expansion Civil Works - PDOC 32' Export Pipeline Segment A1 HPSIC/CPEE Consortium
Client: Petrodar Operating Co Contract Value: 6 million US $ Location: Palouge Duration (month): 21 Months Description: EPCC of PDOC 32' Export Pipeline Segment A1 - Provision of Site Preparation works
Client: Petrodar Operating Co Contract Value: 5.8 million US $ Location: Palouge Duration (month): 12 Months Description: Provision of Site Preparation works , earth works - Adar/Agrodeed Power Distribution System HPSIC Conco Consortium
Client: Petrodar Operating Co Contract Value: 2.4 millino US $ Location: Adar Duration (month): 24 Months Description: Excution ofAdar/Agrodeed Power Distribution System - Bioremediation Expansion Mechanical & Electrical works :
Client: Greater Nile Petroleum Operating Company Contract Value: 2,150,000.00 US $ Location: Higleig Duration (month): 8 Months Description: Bioremediation Expansion Mechanical & Electrical works - Supply of corrugated steel Pipe
Client: Petrodar Operating Co Contract Value: 0.4 millino US $ Location: Port Sudan Duration (month): Description: Supply of corrugated steel Pipe CIF Port Sudan - Field Surface Facilities 2 (Main Contract )
Client: Greater Nile Petroleum Operating CO Contract Value: 3 millino US $ Location: Higleig , Toma South , Eltoor , Elnar & Elhar Duration (month): 4 Months Description: HPSIC carried out the civil works & piles electrical works , e.g driving of pipe (2400). Cleranace of right of way (70km) excavation. The electrical works included the erection of L.V swithgear cabins - Pump station #2 Airstrip
Client: Greater Nile Petroleum Operating CO Contract Value: 1 million US $ Location: Aladalang Duration (month): 3 Months Description: Pump station #2 Airstrip - Fula all weather Road
Client: Greater Nile Petroleum Operating CO Contract Value: 3.5 millino US $ Location: West Kordofan State Duration (month): 7 Months Description: All weather Road 30km. - Produced Water Bioremediation Project ( Main Contract)
Client: Greater Nile Petroleum Operating CO Contract Value: 3.6 million US $ Location: Higleig Area Duration (month): 15 Months Description: The Project is aimed for treating water produced from oil exploration. The porject includes excavation , embankments , pump station , irrigation works. - Produced Water Bioremediation Project ( Main Contract)
Client: China National Petroleum Corporation Contract Value: 3.5 million US $ Location: Higleig Area Duration (month): 18 Months Description: Fula Pipeline Parallel Road 80km. - Pilling of Marine Terminal ( Main Contract)
Client: Techent- Saipem Joint Venture Contract Value: 0.4 millino US $ Location: Marine Temainal -Bashayer Duration (month): 6 Months Description: The work included , the driving of 150 steel piles at the marine terminal to an average depth of 25 m
- Karima Nawa Road
Client: Merwe Dam Implementation Unit Contract Value: 71,147,417.85 US $ Location: Karima Duration (month): 34 Months Description: Engineering & Construction of Karima Nawa Road, the total length of the road is 180km, the work included earthwork, sub-base, base, asphalt & drainage structures. - Merwe Atbra Road
Client: Merwe Dam Implementation Unit Contract Value: 23 million US $ Location: Merwe Duration (month): - Description: Construction of Merwe Atbra Road Total Length 73.5km, poroject consists of Asphalt , base , sub base &drainage structure. - Umdurman - Elmultaga Road Rehabilitation works Merwe Atbra Road
Client: Merwe Dam Implementation Unit Contract Value: 14.5 million US $ Location: Umdurman Duration (month): - Description: Rehabilitation of Omdurman-Elmultaga Road total length 150 km. - Doka Gallabat Road ( Main contract)
Client: National Highway Authority Contract Value: 13.6 million US $ Location: Gadaref State Duration (month): 24 Months Description: The works include the consturction of all seasons road. The total length of road is 80km.The whole works wer carried by HPSIC including the survey works, earth work & drainage structures. Our site laboratory carried all required tests. - Elrank Faluge Road ( Main contract)
Client: Petrodar Operating Co Contract Value: 13.6 million US $ Location: Upper Nile State Duration (month): 20 Months Description: Total Length of Road is 160 km . The works were carried by HPSICS include the Survey works , earth works , R.c.c Bridges & Drainage structures. Out site laboratory crried out all required tests. - Sinar Kosti Road
Client: National Highway Authority Contract Value: 9,930,870.00 US $ Location: Sinar Rabak Duration (month): 34 Months Description: Rehabilitation of Senar Kosti Road - Provision of Access Road
Client: Kahrtoum New International Airport Implimintation Unit Contract Value: 5,772,040.00 US $ Location: Khartoum Duration (month): 20 Months Description: Provision of Access Road - Rehabilitation of Wad-Medni Sinar Road
Client: National Highway Authority Contract Value: 7 million US $ Location: Gezira Duration (month): 11 Months Description: Total Length of Road is 75 km - Provision of Road maintenance equipment & other
associated services ( Main Contracor)
Client: Greater Nile Petroleum Operating CO Contract Value: 5.6 million US $ Location: Higleig Area Duration (month): 36 Months Description: HPSIC provides the customer with the required plant to supply material & construct the civil works. The rental included the earth -moving equipment , trucks , compac tors and cranes ..etc - Provision of Fence & Site Preparation work
Client: Kahrtoum New International Airport Implimintation Unit Contract Value: 4,467,072.00 US $ Location: Khartoum Duration (month): 20 Months Description: Provision of Fence & Site Preparation work - Amri Roads
Client: Merwe Dam Implementation Unit Contract Value: 4.3 million US $ Location: Amri Duration (month): - Description: Construction of Amri New Roaads total length 26km. - Jarayan Lehr Road (Main Contractor)
Client: White Nile Petroleum Operating CO Contract Value: 3.7 million US $ Location: Unity State Duration (month): - Description: The work s included the construction of all seasons' road. The total length of road is 47km. The whole works were carried by HPSIC including the survey works, earth works & drainage structure s.Out site laboratory carried out all required tests. - Merwe Dam Road+ Bridges ( Main contractor)
Client: Merwe Dam Implementation Unit Contract Value: 3.6 million US $ Location: Nile River State Duration (month): 10 Months Description: The works include the consturction of all seasons road. The total length of road is 42km.The whole works wer carried by HPSIC including the survey works, earth work & drainage structures. Our site laboratory carried all required tests. - Construction of Exploration and Security Road in Block #4
Client: Greater Nile Petroleum Operating CO Contract Value: 1.5 million US $ Location: Block 4 Duration (month): 3 Months Description: Construction of Exploration and Security Road in Block #4 - Elmuglad - fula Road Block 6 ( Main contractor)
Client: China National Petroleum Corporation Contract Value: 1.2 million US $ Location: West Kordofan State Duration (month): 3 Months Description: The works include the consturction of all seasons road. The total length of road is 26.5km.The whole works wer carried by HPSIC including the survey works, earth work & drainage structures. Our site laboratory carried all required tests. - Singa Karkog Road
Client: White Nile Petroleum Operating CO Contract Value: 1.3 million US $ Location: Block 8 Duration (month): 8 Months Description: Total Length of Road is 30 km - Construction of Access Road & Gezira-1
Client: Sudapak Contract Value: 0.3 million US $ Location: Gezira Duration (month): - Description: Construction of Access Road & Gezira -1 total length 14.50km
- Karima Internal Roads
Client: Merwe Dam Implementation Unit Contract Value: 84.5 million SDG Location: Northen State Duration (month): 12 Months Description: Internal Roads for Karima - Merwe Internal Roads
Client: Merwe Dam Implementation Unit Contract Value: 42.5 million SDG Location: Northen State Duration (month): 12 Months Description: Internal Roads for Merwe - Pantiyo Electrical Distribution Network
Client: Ministry of Energy and mining Contract Value: 12 Million SDG Location: Pantiyo Duration (month): - Description: Electrical Distribution Network in Pantiyo. - Provision of Water Well Rig & Associated services
Client: Petrodar Operating Co Contract Value: 1.0 million US $ Location: Palouge and Adar Duration (month): - Description: Water Well drilling & Associated Services. - Water Yards and Hand pump installation
Client: Development Fund for South and war Extended Area Contract Value: 0.5 million US $ Location: Kordofan , Bahr El Gazal , Blue Nile State Duration (month): - Description: Water Well Drilling , associated services and Instatllation of hand pump ( about 70 wells) - Palouge Market Electrical (LV) Distribution Network
Client: Ministry of Energy and mining Contract Value: 0.5 million US $ Location: Palouge Duration (month): - Description: Electrical (LV) Distribution Network in Palouge Market - Community Development Project
Client: Ministry of Energy and mining Contract Value: .05 million US $ Location: Higleig Are / Unity State Duration (month): 21 Moths Description: Construction of schools , clinics , water supply , electricity supply project. - Community Development Project
Client: Greater Nile Petroleum Operating CO Contract Value: 0.3 million US $ Location: Higleig Are / Unity State Duration (month): 36 Months Description: The project cosntitues of : High secondary school at Abiee ( 6 classes , 4 offices + 3 compound wall ) . Primary School at Abulikri ( 8 classes , 2 offices ) Primary school at sitaab and Hospital in Mayong.
- Provision of Power Supply
Client: Kahrtoum New International Airport Implimintation Unit Contract Value: 7,946,927.00 US $ Location: Adar Area Duration (month): 21 Months Description: Adar overhead line Phase II - FSF3A electrical Distribution system- long Term contract
Client: Greater Nile petroleum operating company Contract Value: 4.5million US $ Location: Muglad Duration (month): - Description: FSf3A electrical Distribution system- long Term contract - Adar overhead line Phase II
Client: Petrodar Operation Co. Contract Value: 2,270,572.00 US $ Location: Khartoum Duration (month): 21 Months Description: Provision of Power Supply - Electrical Distribution system for FsFA (Block1A)early tie –in wells
Client: Greater Nile petroleum operating company Contract Value: 2.1 Million US $ Location: Muglad Duration (month): 2 Months Description: 33kv - Electrical Distribution system for FSFA (Block1A) early tie –in wells - Submersible pump project (ESP) PHASE2 (Main contractor)
Client: Greater Nile petroleum operating company Contract Value: 1.8 million US $ Location: UNITY STATE Duration (month): 9 months Description: The Project constitutes erection and other connection for submersible pump plus erection - Palouge power Distribution system HPSIC/CONCO Consortium
Client: Petrodar Operating Co Contract Value: 1.6million US $ Location: Palouge and Adar Duration (month): - Description: Execution of palouge power Description system. - Construction of 220 Kv Transmission Line Section (1)
Client: National Electricity Corporation Contract Value: 1,691,273.10 US $ Location: Jabal Awlia Duration (month): 12 Months Description: Construct+B26ion of 220 Kv (Towers foundation) Transmission Line Section (1) - Elgili Shendi Atbara Transmission Line section D(Main contractor)
Client: National Electricity Corporation (NEC) Contract Value: 1.1million US $ Location: Atbra Duration (month): 7months Description: construction of concrete foundation for towers. About 230towers - FSFA electrical Distribution system for Talih Early Tie-in Wells
Client: Greater Nile petroleum operating company Contract Value: 0.9 million US $ Location: Muglad Duration (month): 5months Description: EPCC of Thar Jath export pipeline mechanical,welding of 86 km&civil176kmof 24”pipelinet - Power poles (Main contractor)
Client: Greater Nile Petroleum Operating CO Contract Value: 0.8 million US $ Location: Higleig Are Duration (month): 3 Months Description: The works included the manufacturing 2700 power poles &transported to prescribed locations. - Telecommunicatin Equipment Insallation in pump Station (Main ontractor)
Client: Techint-saipem joint venture Contract Value: 0.5 million US $ Location: Higleig ,Dilling,Elobied &Um sayala Duration (month): 5 Months Description: HPSIC carried out the civil works of the Telecommunicatin towers, repeaters, v-sat antenna &NDB System .the works also including laying of fibre optical - Swittchgear Cabins (Main contractor)
Client: Greater Nile petroleum operating company Contract Value: 0.3 million US $ Location: Higleig Duration (month): 3 months Description: Supply &fabrication of low voltage switchgear cabins .The cabin comprises asteel frame &corrugated iron sheet cladding .The total number of cabins is 90.
Our Locations
A Growing Giant
HPSIC had started out as a small engineering and earth moving company in 1997 at Khartoum, with a handful of employees. As an ambitious national firm involved in the oil and gas field, and through achieving assignment after assignment, Higleig obtained the recognition of the governmental entities, as well as the large operating companies in Sudan.
HPSIC grew steadily along rich and challenging journey that stared in 1997, and decided not to look back but to head forward firmly. It got involved in the various disciplines relevant to the oil and gas, roads and bridges, airports and supply chain.